Facilities Management

$mainhead

Demolition spring/summer 2016

Holes Hall Demolition

Live webcam

View full size

From 1965-2014, Holes Hall was home to tens of thousands of St. Cloud State students. Its small rooms, modest amenities and large, common bathrooms no longer appeal to young people. University leaders, MnSCU officials and construction consultants have deemed it cost-prohibitive to remodel.

For the near term, Holes Hall will be demolished and the site will be converted to green space.

In months leading up to the demolition, St. Cloud Fire Department and St. Cloud Police Department have used Holes Hall as a training site.

2016 Demolition schedule

March 28 - Asbestos abatement start

May 13 - Asbestos abatement completed

May 16 - Delivery of equipment and fencing

June 1 - Demolition begins

Aug. 17 - Demolition substantial completion

  • All demolition complete, all demo equipment removed
  • Site filled and rough grading completed
  • Parking lots and sidewalks clean
  • Demolition construction fence relocated for site restoration

Aug. 31 - Demolition site restoration start

Sept. 15 - Demolition final completion